under construction

Design of Gym and Two Early Childhood Classrooms

Construction Project Rendering

Project Updates

September 1, 2023

The mason had to shut down all last week due to the heat. This has affected his schedule on all projects, thus now it will be sometime the during the week of September 11 to the 15 before the mason work will begin. The new timeline is as follows:

  • Hoelscher Interiors is on site now working on studs and exterior sheathing.

  • Mason will start sometime during the week of 09-11-23 to 09-15-23.

  • Iron worker will start after mason gets masonry wall along the existing building completed which should fall between 09-13-23 to 09-20-23 depending on when block wall gets done.

  • Roofing will start between 09-20-23 to 10-09-23 Depending on when roof decking is completed and all exterior brick work is completed.

  • Hoelscher Interiors will insulate exterior walls and interior sheathing after roofing is installed.

August 25, 2023

Completed: All the building concrete footings, foundations, and floor slab

Erected: Structural steel frame

Installed: 1/2 of the metal roof deck

Due to excessive heat this week, the metal stud work will begin on Monday August 28.

After the metal exterior studs and exterior sheathing is completed, the mason will brick up the exterior brick veneer walls. The mason is schedule to be on site in two weeks. They will first lay up the interior block wall against the existing building. Once the interior block wall against the existing building is completed, the Iron workers will come back to finish up the metal roof deck and P-angles. Then the masons will work on the exterior brick. Once the iron workers are done with the metal deck, the roofers will come and install the roofing. After the roof is installed and the exterior brick work is completed, Hoelscher Interiors will insulate the walls and install any interior sheathing.

Summary:

  • Stud & Sheathing - Start 08-28-23

  • Mason - Start 09-04-23

  • Iron Worker - Start 09-06-23 to 09-08-23 depending on when block wall gets done

  • Roofing - Start between 09-11-23 to 09-18-23 depending on when all blocking gets installed

August 7, 2023

It's a busy day on the construction site as the concrete for the classroom floors is being poured. The floor will need about a week to cure. If all goes well, Lake Contracting, Inc. will start setting steel next Monday. Less than 2 months into the project, the structure will start taking shape.

July 13, 2023

It's a busy day on the construction site as the footings are being poured.

June 29, 2023

t's been a busy week on the construction site. The Munster Street entrance is officially open, and the entrance along Walnut Street is now closed. Concrete removal is taking longer than anticipated due to the discovery of another layer of concrete, the foundation of the original three story schoolhouse that was once standing on the site.

There will be no action on site June 30-July 4. Next steps include laying out forms, excavating forms, and pouring piers and footings.

Stay tuned for more updates as, brick by brick, we watch our vision become reality.

June 26, 2023

The construction project is currently running ahead of schedule.  The work associated with the new entrance has been completed.  Tomorrow afternoon, the new entrance will be opened and the original entrance will be closed.  

The process of removing the concrete from the 'exit lane' of the original entrance has begun leaving only one lane to enter and exit the parking lot.  Once the new entrance is opened and the original entrance is closed, the remaining concrete from the original entrance will be removed and the process of preparing the site for the construction of classrooms will begin.

Starting tomorrow afternoon, please plan to use the entrance located across from Valbo's along Munster Street to enter/exit the parking lot area.  The 'alleyway' between the school and the rectory/parish garage is a one way exit only.  

June 16, 2023

At our pre construction meeting yesterday, we were given a tentative timeline for what to expect throughout the project.  Below are some key dates:

  • Tuesday, June 20:  Begin work on new entrance which will be located across the street from Valbo’s.  This will involve mobilizing the site, setting up a safety fence, and some saw cutting.

  • Wednesday, June 21:  Fence Demo Day  

  • June 22-28: Construct New Entrance

  • July 5-6:  Demo Existing Entrance

  • Tuesday, July 25: Construction Pauses for Parish Picnic.

  • December 29:  Classroom Project Completed

Please note that the current entrance to the parking lot will remain open until the new entrance is completed.

We will continue to provide updates as we make our way through the project.  For now, the main thing to note is that we will start seeing some action on site next week. 

Click here to access the project timeline.

June 13, 2023

The construction project is slated to begin on June 19.

The project will start with the construction of the new entrance across the street from Valbo's.  If all goes as planned, the new entrance will be completed mid to late week the first full week of July.

The current entrance to the parking lot will remain open until the new entrance is completed.

Once the new entrance is completed, construction will begin on the classrooms, and the current entrance will be closed.

The staging area for the construction project will be the grassy area to the west of the construction site.  The entire stretch of land extending from the west wing to the fence will be closed off for construction purposes.  

We have a pre-construction meeting on Thursday, June 15. Any updates will be shared with the school community.

The contractors for the project include:

General Contractor: Lake Contracting, Inc.

Plumbing Contractor: Kohnen Air Conditioning & Heating

Mechanical Contractor: Kohnen Air Conditioning & Heating

Electrical Contractor: Kohrmann Electric, Inc.

June 2, 2023

It has been a long time coming, but phase 1 of the construction project is slated to start this month.  This phase includes the addition of 2 classrooms on the west wing of the school building.  Carl and I participated in a pre construction meeting yesterday morning.  We walked away from this meeting with the following information:

We still do not have a firm start date on construction.  The holdup is rebar.  We anticipate the project will get underway later this month.  It is slated to be completed by January 1, 2024.

The first task to complete will be the new entrance which will be located across from Valbo's.  Once completed, it will have to sit for a week before it can be used.  The original entrance will remain open until the new entrance can be used.  We are told the new entrance will be ready prior to the picnic which is Tuesday, July 25. At that point, the old entrance will no longer be accessible.  The grassy area west of the construction site will be the staging area. The entire stretch of land extending from the west wing to the fence will be closed off for construction purposes.  

Other than a day here and there, Walnut Street will remain open throughout the project. 

As the construction timeline evolves, updates will be shared with all members of the school community. 

You might be wondering the status of phase 2, the gym.  We are in the beginning stages of coordinating a capital campaign to raise money to fill the funding gap.  If you are interested in helping out with the campaign, let me know.  

January 27, 2023

We were notified this week by the Capital Development Board that our early childhood construction grant was not funded.  While I was naturally disappointed with this news, I cannot say it surprised me as we are not considered a ‘needy’ district despite being underfunded by about $800,000 in FY22.  Where funding is concerned, a Percent of Adequacy rating is given to every school district in Illinois.  Our Percent of Adequacy as noted on the 2021-22 Illinois School Report Card is 71%.  In a nutshell, that number depicts our school funding at 71% of what it should be.  As the challenges we face in education increase, school funding is not.  I am sure you can imagine that being inadequately funded by 29% makes for a very tight budget.

Now that we know we were not awarded the Early Childhood Construction Grant, what next?  We shift to Plan B which is a 2 phase approach.  Phase 1 will include the addition of 2 classrooms.  The classrooms are needed in order to accommodate the increase in enrollment we are experiencing due to community growth.  At the February board meeting, we anticipate reviewing and approving bid document revisions, so that we can move forward with securing bids for the classrooms.  The hope is that construction of the classrooms will start immediately after the conclusion of the 2022-23 school year.  

While Phase 1 is in progress, we will continue to look for ways to close the funding gap for Phase 2, the gym project.  Right now, that gap stands at approximately $600,000 which is a rather significant amount of money.

December 27, 2022

After finding out that the announcement of the early childhood construction grants was being pushed back to at least mid-January, we were presented with the following options to choose between:

Option #1: Wait on the Early Childhood Construction Grant Award announcement in January 2023. If we receive the grant, we award to low responsive bidders. With this scenario construction on the classrooms and gym could begin in February depending on when the award announcement is made.

Option #2:  We reject all bids and redirect Lunsford to rebid with a base bid to construct two classrooms and an alternate bid to add gym.  We rebid in January, award bid in February, and begin construction on the classrooms in March at the earliest. Construction on the gym would wait until the funding gap is filled.

Given that neither option will allow for classrooms to be finished for the start of the 2023 school year, we chose Option #1.  At this point, waiting a little longer for the Early Childhood Construction Grant Award announcement really doesn’t hurt anything. 

If awarded the Early Childhood Construction Grant, the construction of the early childhood classrooms and gym will begin as soon as possible. With no grant funding, we will begin phase 1 of the construction project, the early childhood classrooms, and follow-up with phase 2, the gym, as soon as the funding gap is filled.

December 5, 2022

We finally received some guidance on the direction we need to go with the construction project.  Here is a quick recap of the situation:

  • We had our bid opening meeting in November. Unfortunately, due to the state of inflation and the associated high costs of essential materials and skilled labor, the project came in over budget between $375,000-$600,000. We cannot simply borrow more money as school’s have a debt limit directly associated with the EAV of the school community.  At this time, we have reached that debt limit and do not have the option to borrow more money. So what next? 

  • In July, a grant for early childhood construction was released.  We wrote and submitted for a $3.3 million dollar grant.  Grant awards were slated to be announced in November.  At the time, it made sense to wait for the grant announcement before making a decision on next steps. Getting the grant would allow us to move forward with the project as planned. If the grant was not funded, we would switch to a 2 phase construction project, phase 1, the classrooms, followed by phase 2, the gym.  The construction of the classrooms is a topmost priority as we are out of space. While moving forward with the classroom phase of the project, we would work on securing funding to fill the gap for the gym project.

  • On the grant announcement page, it clearly indicates that the “CDB expects to make award announcements in November 2022”, thus the reason we were in a holding pattern on the project.  We anticipated knowing the status of the grant by the end of November.  As of November 30, I had yet to hear from the Capital Development Board on the status of the grant, so I emailed them.  To my dismay, we were told not to expect any results until at least the middle of January.  With that being said, given that we need to get the classrooms started as soon as possible, we will be moving forward with the 2 phase approach to the project. We are working closely with the architect to get the classroom phase of the project started as soon as possible. When we have more information to share, we will let you know.

While it is frustrating that nothing seems to be going as planned on this project, I am choosing to focus my energy on what we can control, making sure we have everything on our end ready to go for this project. I am grateful that we have this opportunity to expand, and I look forward to overcoming the challenges we face to make the finished product one that we will all be proud of.

November 10, 2022

Good morning Bulldog Country.  As we approach the midway point of the second quarter, I thought I would share an update with you.

We continue to work behind the scenes on our labor of love, the impending construction project.  I call it a labor of love because we have already overcome several obstacles, and construction hasn’t even begun yet.  Our latest and greatest obstacle reared its ugly head last Wednesday when we conducted our bid opening meeting.  While the meeting in and of itself went fine, the end result is what we have been worried about all along given the state of inflation and the associated high costs of essential materials and skilled labor.  The project came in over budget between $375,000-$600,000.  

A project being over budget by this amount of money is no small obstacle.  We cannot simply borrow more money as school’s have a debt limit directly associated with the EAV of the school community.  At this time, we have reached that debt limit and do not have the option to borrow more money.  

We were asked by our architect if we were willing to make rather significant concessions on the design:  eliminate the locker rooms, install a cheaper gym floor, etc.  Our response to that question was a resounding no.  This is our ‘forever’ gym.  This gym will be the site of countless concerts, graduations, and athletic events for years to come.  If we are going to do this project, we are going to do it right.

So what next?  There is a glimmer of hope.  In July, a grant for early childhood construction was released.  A total of $60 million dollars will be awarded.  Because the two classrooms we will be adding on will be early childhood classrooms and the additional gym will allow for our PreK Program to conduct gross motor time indoors on days when the weather does not allow for them to go outside, our construction project qualifies as an early childhood construction project.  We wrote and submitted for a $3.3 million dollar grant in early September.  Grant awards are slated to be announced in November.  This grant opportunity gives us hope that we can secure the money we need to fill the funding gap.  In the days to come if you find a lucky penny, see a shooting star, or are a believer in the power of prayer, we would appreciate your help with ‘willing’ this grant to come through for us.  

What if we don’t get the grant?  Then, we switch to a 2 phase construction project, phase 1, the classrooms, followed by phase 2, the gym.  We move forward with the construction of the classrooms first because we are out of space, and that is our topmost priority.  In the meantime, we work on securing funding to fill the gap for the gym project.

One option for funding is called the County School Facilities Sales Tax.  What is the County School Facilities Sales Tax?  It is a 1% sales tax on everything that is currently taxed in the municipality and county.  The tax is NOT applied to:  cars, trucks, ATVs, boats, RVs, mobile homes, unprepared food, drugs including over the counter drugs and vitamins, farm equipment/parts, and services.  If it is NOT currently taxed, it would NOT be taxed.

Why would we support another tax?  The money raised through this tax can only be spent on the following:  facility improvements including additions and renovations, the refunding of bonds, school resource officers, and mental health experts.  Based on the most recent sales tax revenue data from 2021, our school district would have gotten upwards of $200,000 from this sales tax revenue.  That money would be an annual revenue source and would be allocated to paying off our bonds thus lowering the school tax rate in addition to completing upgrades to the facility without having to borrow money, saving the taxpayers even more money.  In reality, this tax would help to lower our school tax rate while allowing for improvements to our facility.  At the same time, outside visitors to Clinton County would be helping to pay for these improvements.  For example, when thousands of visitors from outside Clinton County flock to Carlyle Lake every summer and make purchases at local stores, they would be helping to fund our facility improvements while also serving to lower our school tax rate.  When Centralia High School hosts its annual holiday basketball tournament and visiting teams spend money at stores located in Clinton County, such as the Centralia Walmart, they would be helping to fund our facility improvements while also serving to lower our school tax rate. 

As a taxpayer myself, I would love for my local schools to be able to make facility improvements while at the same time my real estate taxes go down.  As a superintendent, I see this as a win-win.  With a 1% sales tax, our school district would secure additional funding to pay off debt and make improvements to the facility (WIN) while also lowering our school tax rate (WIN).

More information about this funding opportunity will be made available to our school community in the weeks and months to come.  In the meantime, we will continue to work behind the scenes to find a way to close the funding gap for our construction project.

While faced with challenges such as we have faced with this project,we must remind ourselves that all good things take time.  Just like many members of our school community, we have our heart set on seeing this project through and will do everything possible to make it happen.  Please trust that as a school district we are working diligently behind the scenes to be fiscally responsible while working to ensure that the future needs of our school district are being met.